There has been no mistaking the progress on the La Salle School of Business building this spring, with the steel frame soaring skyward as construction moves on pace toward a January 2016 grand opening.

The structural steel framing of the three- and six-story portions was completed in April, and the frame of the facility’s lecture hall was completed in May. Framing of the final portion, the atrium, was expected to be completed in early June.

On the building’s exterior, masonry work has begun on the three-story portion of the building, and brickwork will continue throughout the summer.

Inside, interior partition framing is complete in the three-story building and well under way in the six-story building. The skylight for the atrium arrived and was lifted into place May 29.